February 7, 2022Updated April 20, 2026By Nick PiskuraReading time: 9 minutes
Key takeaways
Any shutdown longer than three days is an extended shutdown. Untreated water left in the system lets Legionella grow and corrodes components.
Before shutdown: raise bleed-off a few days ahead, add extra biocide about a day ahead, then drain the whole system at its lowest point.
At startup: clean and inspect, treat with biocide, chlorinate with sodium hypochlorite for 6 hours, and don’t start the fan until chlorination is done.
Spring and fall are times for normal cooling tower maintenance, as staff performs their normal shut-down-startup routines. While there’s typically a lot of focus on the equipment procedures, proper water handling needs to be considered as well to avoid not only corrosion but bacterial growth. Here are common best practices to follow during seasonal maintenance.
How Do You Shut Down a Cooling Tower?
When temperatures fall and you no longer need your cooling system, it is time to shut down the cooling tower. Leaving untreated water in the cooling system will allow bacteria like Legionella to grow unchecked and corrode critical components, endangering workers and the public and possibly damaging your cooling tower, chillers (if used), heat exchangers and other equipment. This can cause prolonged downtime, affect cooling tower efficiency and increase costs, in addition to creating potential health and safety issues.
Check your manual first
For the purposes of this post, it is not possible to cover every detail, but you will find important maintenance tips for shutdowns and startups. Most important, be sure and check your cooling tower manufacturer’s operation and maintenance guide for specific instructions unique to your cooling tower and cooling system setup.
What Is an Extended Shutdown for Cooling Towers?
3+ days
Extended shutdown
Anything in excess of three days is considered an extended shutdown. Follow the guidelines below to help protect your cooling system throughout the winter season. This will help ensure an error-free startup when warmer weather returns.
Shutting down for winter?
Preparing for shutdown or startup?
Don’t leave corrosion or bacteria to chance. Lay your cooling tower up right before the first hard freeze, and let ChemREADY review your cooling tower water treatment plan before seasonal changes hit.
When Should You Drain a Cooling Tower Before Shutdown?
Work through the shutdown in this order:
1A few days before: increase bleed-off. A few days before you shut down the cooling tower, it is recommended that you rid the system of any solid material by dialing up the system bleed-off. Refer to your maintenance manual for specifics.
2About one day before: add extra biocide. As the shutdown date approaches, approximately one day in advance, add extra biocide to the system (nonoxidizing biocide, if available) and let it circulate in the system for several hours. This will help sanitize the cooling tower system and eliminate biofilm. Check the manual from your manufacturer for more details about this procedure. ChemREADY has a complete line of Kool Tower scale and corrosion inhibitors. If you have any questions about biocides, contact our experts at ChemREADY.
3Isolate pumps, fans, and makeup water. If your unit sits on vibration isolators or isolation rails, reference the specific manufacturer’s operation and maintenance guide before loading or unloading weight from the unit. Uninstall and perform a tag-out on all pumps and fans and shut off the valve in the makeup water line.
4Drain the entire system at its lowest point. To prevent bacterial overgrowth, be sure to drain the entire cooling system at its lowest point, including the chiller, if installed. Remove dirt, trash, leaves and any other foreign materials from inside and outside of the unit. Don’t forget to check the louvers or inlet shields.
5Clean the deck, fill, sump, and basin. Clean the distribution deck, drain and wash the tower and the tower fill and sump. Uninstall the tower conductivity probe and turn off the tower controller, but do not disconnect it from power. Clean and flush the cold-water basin. Make sure the cold-water basin remains open so that precipitation will continue to drain from the tower. Disconnect and clean the strainers, and then reinstall them. Place a cover over the fan discharge unit to keep out dirt and debris. Check any nozzles for clogs and clear any you find.
6Lubricate, rust-proof, and lock out the fan. Lube the motor base adjustment screw and fan shaft bearings. Apply a coat of rust preventative to stop corrosion of shafts. In addition, inspect and repaint any scratched or peeling finish to further protect equipment from rust and corrosion. See your manufacturer’s maintenance guide for finishing specs. Be sure and lock the fan motor starter in the “off” position to prevent accidental startups. We recommend that you add an anticorrosion product to the system to protect components during the shutdown.
7Open and clean the chiller. If your system has a chiller installed, open the end bells and brush the condenser tubes to ensure that no water sits in the chiller and becomes stagnant, which can lead to bacteria growth. Chemically clean the chillers, if necessary, and leave the end bells uninstalled during the duration of the shutdown period. Inspect the heat exchange surfaces, clean, if necessary, and drain and leave them open for the winter.
See white scale or corrosion?
If you see white scale or corrosion, we recommend contacting the experts at ChemREADY, and we will assess your system and change your chemical treatment plan to prevent future problems.
Cooling tower services
Protect your cooling tower during extended downtime
Extended shutdowns increase the risk of biofilm, corrosion, and Legionella growth. Get expert guidance on proper biocide treatment and system preparation.
When the weather warms, it is time to restart your cooling tower system. The startup process includes three main steps: cleaning, inspection and startup.
What Are the Cleaning and Inspection Procedures for Starting Up a Cooling Tower?
1Flush the basin. Leaving the strainer in place, flush and drain the cold-water basin to remove any debris or dirt.
2Inspect the fan deck and fan. Clean and visually inspect the fan deck, clean the fan guards and check the spray nozzles for clogs. Inspect the fan for damage and check the fan blade tips for proper clearance to avoid potential damage upon startup. Do a thorough check of the fan and the fan motor. If you properly lubricated the components, these should be in good shape.
3Check for leaks and damage. Check all equipment for leaks, rust, corrosion or damage, and check for damage to the unit structure itself, including mechanical parts. Look closely at pipe connections to make sure there is no damage or leaks.
4Test the motor and drive. Before starting the motor, be sure and use an insulation tester to check the integrity of the motor’s insulation. Inspect the belt tension, and make sure the gear drive oil level is to spec. Make sure the makeup valve is operating freely. Relubricate the motor base adjustment screw and fan shaft bearings.
5Protect shafts and fill the basin. Apply a rust inhibitor to the steel shafts. Then, use the make-up valve to fill the cold-water basin up to the overflow level with fresh water. Adjust the make-up valve float to ensure that it shuts off water inflow when the level reaches proper operating level.
6Balance flow and bleed. If applicable for your system, check the drain plug. During the first day after startup, monitor the water level and adjust as required. Adjust flow balancing valves for the top inlets. If your system is configured with multiple cells, make sure the water levels are evenly distributed across all cells. Adjust the tower bleed line valve until the bleed rate is optimized. Inspect all nozzles.
How Do You Treat the Water and Restart the Fan?
1Treat with biocide. Before starting the fan, treat with a biocide at a level and for a period recommended by the biocide supplier, or contact ChemREADY for recommendations.
2Check pH and chlorinate. Check the water’s pH and adjust if necessary (check the manufacturer’s guidelines). Treat with sodium hypochlorite for 6 hours to achieve the proper chlorine concentration. You can use a commercially available test kit to measure free chlorine.
3Start the fan only after chlorination. Do not start the fan until the chlorine treatment is completed. Power up the fan motor and check the direction of the fan’s rotation, and make sure it is turning in the proper direction, as shown by the arrow on the cowl (if your unit has a gear drive system, consult the manufacturer’s guidelines).
4Listen and check the motor. Temporarily operate the fan manually and note any tell-tale noises or vibrations. After startup, make sure the voltage and current do not exceed the specifications on the motor’s nameplate.
Remember, this list is not all-inclusive, and you should consult the manufacturer’s operation and maintenance manual for your specific unit.
Need Help With Your Cooling Tower Shutdown and Startup?
For advice and consultation on the proper chemicals to use during your cooling tower shutdown, contact the experts at ChemREADY and let us help. We will assess your needs and provide the best advice for keeping your cooling tower ecosystem free from stagnation, corrosion and bacterial contamination. Our complete line of Kool Tower scale and corrosion inhibitor products are a great choice for protecting your cooling tower system.
From biocides to corrosion inhibitors, ChemREADY provides the right chemicals and expertise to keep your cooling tower protected year-round. Close out 2026 with a year-end water treatment check before spring startup.
Frequently Asked Questions About Cooling Tower Shutdown and Startup
What is an extended shutdown for a cooling tower?+
Anything in excess of three days is considered an extended shutdown. Follow shutdown guidelines to help protect your cooling system throughout the winter season and help ensure an error-free startup when warmer weather returns.
Why shouldn’t you leave untreated water in a shut-down cooling tower?+
Leaving untreated water in the cooling system will allow bacteria like Legionella to grow unchecked and corrode critical components, endangering workers and the public and possibly damaging your cooling tower, chillers (if used), heat exchangers and other equipment.
When should you drain a cooling tower before shutdown?+
A few days before shutdown, dial up the system bleed-off to rid the system of solid material. About one day in advance, add extra biocide (nonoxidizing, if available) and let it circulate for several hours. Then drain the entire cooling system at its lowest point, including the chiller, if installed.
What are the steps to start up a cooling tower?+
The startup process includes three main steps: cleaning, inspection and startup. Before starting the fan, treat with a biocide at the level and for the period recommended by the biocide supplier, check and adjust pH, and treat with sodium hypochlorite for 6 hours to achieve the proper chlorine concentration.
When can you start the cooling tower fan after shutdown?+
Do not start the fan until the chlorine treatment is completed. Then power up the fan motor, confirm it turns in the direction shown by the arrow on the cowl, and make sure voltage and current do not exceed the motor’s nameplate specifications.
Buyer’s guide
Evaluating cooling tower water treatment programs?
A practical buyer’s guide covering chemistry, service levels, and total cost of ownership before you sign anything.
Are you an M&A advisor or PE firm? We work with advisors who encounter infrastructure gaps in client businesses. If you’re looking for a referral partner for pre-sale readiness work, learn about our partner program.
Nick Piskura is the Marketing and Web Development Specialist at ChemREADY who utilizes expertise in digital marketing strategies to provide knowledgeable insights in each segment of our business.
Technically reviewed by the ChemREADY cooling tower services team.
Year-end water treatment checkShutting your cooling tower down for winter?We’ll check your cooling tower chemistry and treatment plan and send a plain-English report. No obligation.